McARTHUR RIVER MINE

Tailings System Upgrade

Client: McArthur River Mine
Location: Northern Territory
Services Provided: EPCM
Completion:
June 2008
Product: Lead Zinc Silver
Project Value: A$15 million

--- Projects -McARthur River Copy

Our Role

Provision of engineering, project and construction management services for the upgrade of existing tailings system including the installation of a new 36m diameter high rate thickener, tailings pumps and 3km of tailings pipeline. The upgrade was part of a suite of projects to increase concentrator capacity to 2.5Mtpa.

Project Outcomes

Optimum design of the new tailings line allowed the operation to run at reduced pumping  power and save substantial power as a result.